Location shortlist / 61 sites

North America

US and Canadian deployments, from dedicated GPU halls to new campus plans. This view includes 61 sourced records. Delivered and planned MW sit in separate columns, each tied to its source.

Locate sites on the map · Read the capacity definitions

Applied Digital Delta Forge 1Applied DigitalBoyceUnited StatesInfrastructure developerUnder construction—3001Contracted critical IT load; hyperscaler unnamed.—2026-11-11
Applied Digital Polaris Forge 2Applied DigitalHarwoodUnited StatesInfrastructure developerUnder construction—2001Contracted critical IT load; hyperscaler unnamed.—2026-11-11
Core42 DallasCore42DallasUnited StatesGPU / AI deploymentOperational————2026-11-11
Core42 Lake MarinerCore42BarkerUnited StatesGPU / AI deploymentOperational601—Core42 production AI infrastructure after expansion; separate from Fluidstack leases.AMD Instinct MI300; additional NVIDIA and AMD infrastructure2026-11-11
Core42 MinneapolisCore42MinneapolisUnited StatesGPU / AI deploymentOperational————2026-11-11
Core42 StocktonCore42StocktonUnited StatesGPU / AI deploymentOperational————2026-11-11
Core42 SunnyvaleCore42SunnyvaleUnited StatesGPU / AI deploymentOperational————2026-11-11
CoreWeave at DentonCoreWeaveDentonUnited StatesGPU / AI deploymentOperational26032603About 260 MW billing of 260 MW leased critical IT (Core Scientific, 5 Nov 2026).—2026-11-11
CoreWeave AustinCoreWeaveAustinUnited StatesGPU / AI deploymentOperational201201About 20 MW billing of 20 MW leased critical IT (Core Scientific, 5 Nov 2026).—2026-11-11
CoreWeave DaltonCoreWeaveDaltonUnited StatesGPU / AI deploymentOperational7511751About 75 MW billing of 175 MW leased critical IT (Core Scientific, 5 Nov 2026).—2026-11-11
CoreWeave DouglasvilleCoreWeaveDouglasvilleUnited StatesGPU / AI deploymentAnnounced—91Announced allocation at each facility in the 2023 agreement.—2026-11-11
CoreWeave Ellendale Polaris Forge 1CoreWeaveEllendaleUnited StatesGPU / AI deploymentOperational17514001Contracted critical IT load across the campus; phased delivery.—2026-11-11
CoreWeave HeliosCoreWeaveAftonUnited StatesGPU / AI deploymentOperational1333—Phase I delivered critical IT load, in service at quarter end; 200 MW gross is a different measure.—2026-11-11
CoreWeave HillsboroCoreWeaveHillsboroUnited StatesGPU / AI deploymentAnnounced—91Announced allocation at each facility in the 2023 agreement.—2026-11-11
CoreWeave Kenilworth NEST 11CoreWeaveKenilworthUnited StatesGPU / AI deploymentUnder construction————2026-11-11
CoreWeave LancasterCoreWeaveLancasterUnited StatesGPU / AI deploymentAnnounced—1001Initial facility plan; potential expansion to 300 MW—2026-11-11
CoreWeave MarbleCoreWeaveMarbleUnited StatesGPU / AI deploymentOperational651651About 65 MW billing of 65 MW leased critical IT (Core Scientific, 5 Nov 2026).—2026-11-11
CoreWeave MuskogeeCoreWeaveMuskogeeUnited StatesGPU / AI deploymentOperational701701About 70 MW billing of 70 MW leased critical IT (Core Scientific, 5 Nov 2026).—2026-11-11
CoreWeave PlanoCoreWeavePlanoUnited StatesGPU / AI deploymentAnnounced————2026-11-11
Crusoe Abilene MicrosoftCrusoeAbileneUnited StatesGPU / AI deploymentUnder construction—9001New dedicated campus with on-site power; not operating IT load.—2026-11-11
Crusoe Abilene StargateCrusoeAbileneUnited StatesGPU / AI deploymentOperational———NVIDIA GB2002026-11-11
Crusoe HoustonCrusoeHoustonUnited StatesGPU / AI deploymentOperational————2026-11-11
Crusoe SparksCrusoeSparksUnited StatesGPU / AI deploymentOperational————2026-11-11
Crusoe Wyoming former projectCrusoe—United StatesHistorical projectWithdrawn / transferred————2026-11-11
Fluidstack Barber LakeFluidstackColorado CityUnited StatesGPU / AI deploymentUnder construction—1681Contracted critical IT load; delivery targeted September 2026 in the filing.—2026-11-11
Fluidstack Lake MarinerFluidstackBarkerUnited StatesGPU / AI deploymentOperational————2026-11-11
Hyperstack / NexGen MontrealHyperstack / NexGenMontrealCanadaGPU / AI deploymentOperational————2026-11-11
Hyperstack / NexGen US-1Hyperstack / NexGen—United StatesGPU / AI deploymentOperational————2026-11-11
IREN Canal FlatsIRENCanal FlatsCanadaAI use unconfirmedStatus unconfirmed—301Existing campus power; GPU-specific portion undisclosed.—2026-11-11
IREN Childress Horizon 1IRENChildressUnited StatesGPU / AI deploymentOperational501—Horizon 1 critical IT load; excludes Horizon 2–4 and other campus usesNVIDIA GB300 NVL722026-11-11
IREN MackenzieIRENMackenzieCanadaGPU / AI deploymentOperational801—Approximately 80 MW total campus capacity as of 2025-12-31—2026-11-11
IREN Prince GeorgeIRENPrince GeorgeCanadaGPU / AI deploymentOperational501—Approximately 50 MW total campus capacity as of 2025-12-31—2026-11-11
IREN SweetwaterIRENSweetwaterUnited StatesGPU / AI deploymentUnder construction—2,0001Campus power under construction, not GPU IT load.—2026-11-11
Lambda Atlanta ATL02LambdaAtlantaUnited StatesGPU / AI deploymentOperational————2026-11-11
Lambda Chicago AI factoryLambdaChicagoUnited StatesGPU / AI deploymentUnder construction—231Planned single-tenant data center capacity; IT/gross split unspecified—2026-11-11
Lambda Kansas City AI factoryLambdaKansas CityUnited StatesGPU / AI deploymentStatus unconfirmed—241Announced launch capacity; not verified operating capacityNVIDIA Blackwell Ultra2026-11-11
Lambda Mountain View MV1LambdaMountain ViewUnited StatesGPU / AI deploymentOperational———NVIDIA GB300 NVL722026-11-11
Lambda Plano DFW-04LambdaPlanoUnited StatesGPU / AI deploymentUnder construction————2026-11-11
Lambda Vernon LAX01LambdaVernonUnited StatesGPU / AI deploymentOperational211—Initial Lambda lease allocation; not the full 33 MW facilityNVIDIA Blackwell2026-11-11
Nebius IndependenceNebiusIndependenceUnited StatesGPU / AI deploymentUnder construction—1,2001Up to 1.2 GW total campus ambition; not live power—2026-11-11
Nebius Kansas CityNebiusKansas CityUnited StatesGPU / AI deploymentOperational—403Initial 5 MW, expandable to 40 MW (Nebius, Nov 2024).NVIDIA H200; NVIDIA B2002026-11-11
Nebius VinelandNebiusVinelandUnited StatesGPU / AI deploymentOperational—3002Up to 300 MW phased design capacity (Nebius, March 2025).—2026-11-11
Nebius WoodburyNebiusWoodburyUnited StatesGPU / AI deploymentOperational———NVIDIA B300 NVLink2026-11-11
Nscale MadisonNscaleMadisonUnited StatesGPU / AI deploymentAnnounced—401Capacity expected online in 2026; 99 MW secured power is a separate scope.—2026-11-11
Nscale MonarchNscale—United StatesGPU / AI deploymentAnnounced—1,3501Phase 1 engineered AI capacity; target early 2028.—2026-11-11
Nscale Ward CountyNscaleWard CountyUnited StatesGPU / AI deploymentOperational—2001Approximate IT load supported by financed deployment; not verified live drawNVIDIA GB300 and Vera Rubin VR200 (financed deployment)2026-11-11
Together AI Maryland 5CTogether AI—United StatesGPU / AI deploymentOperational———NVIDIA B2002026-11-11
Together AI Memphis 5CTogether AIMemphisUnited StatesGPU / AI deploymentAnnounced———NVIDIA GB200 and GB300 (planned)2026-11-11
Voltage Park AllenVoltage ParkAllenUnited StatesGPU / AI deploymentOperational———NVIDIA H100 80 GB SXM52026-11-11
Voltage Park QuincyVoltage ParkQuincyUnited StatesGPU / AI deploymentOperational———NVIDIA H100 80 GB SXM52026-11-11
Vultr AtlantaVultrAtlantaUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr ChicagoVultrChicagoUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr DallasVultrDallasUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr HonoluluVultrHonoluluUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr Los AngelesVultrLos AngelesUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr MiamiVultrMiamiUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr PiscatawayVultrPiscatawayUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr San JoseVultrSan JoseUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr SeattleVultrSeattleUnited StatesGeneral cloud footprintOperational————2026-11-11
Vultr SpringfieldVultrSpringfieldUnited StatesGPU / AI deploymentAnnounced—501Announced additional supercluster deployment; no commissioning confirmation in this release.AMD Instinct MI355X2026-11-11
Vultr TorontoVultrTorontoCanadaGeneral cloud footprintOperational————2026-11-11

Other shortlists

  • Operating deployments — Locations with a public operational statement. Expansion capacity may still be planned.
  • Construction & plans — Announced facilities, construction projects and unresolved delivery status.