Nscale / United States

Nscale Ward County

Nscale’s Ward County AI data center is live, while its financing supports a larger future GPU deployment.

Operational

Sources checked

October update confirms a live data center with thousands of GPUs. The August financing describes approximately 200 MW IT load; this is not a measured operational load. Location is county-level.

Open official site evidenceCompare locationsRequest a quote

Site evidence

Source per value
Operator GPU-cloud provider tied to this physical site.
Nscale 1
City / locality Source-named city, metro or locality. Null when only a county, state or dedicated regional facility is disclosed; no guessed city.
Ward County 2
Country Country of the physical deployment.
United States 1
Evidence status Status supported by the cited evidence. An operational site may also have future expansion; target dates alone do not prove opening.
Operational 2
Facility / partner Named host, owner or development partner; role shown where stated.
Ionic Digital 3
Disclosed power MW Read together with Power basis. This may be an IT lease, campus plan, facility capacity or a delivered phase; values must not be summed.
200 1
Power basis Scope, timing and qualification of the disclosed MW. Operational status does not imply all listed MW are live.
Approximate IT load supported by financed deployment; not verified live draw 1
GPU platform Site-specific deployed or announced platform. Expansion and future deployment are explicitly marked.
NVIDIA GB300 and Vera Rubin VR200 (financed deployment) 1
Disclosed GPUs Published count, approximation or lower bound. Read GPU count basis for deployed versus planned scope.
Not published
GPU count basis Exact scope of the GPU count, including lower bounds and target years. Counts are not a current availability inventory.
Not published
Interconnect Site-specific networking named in the source; no inference from a provider-wide offer.
Not published
Cooling Cooling design or installed method at the site; expansion scope retained where relevant.
Closed-loop direct liquid cooling and rear-door heat exchangers 1
Evidence date Date of the cited status statement or reporting period. Null means an undated page; accessed dates remain in sources.
2026-10-01 2
Scope notes Research reconciliation, historical qualifications and unresolved delivery questions, with sources.
October update confirms a live data center with thousands of GPUs. The August financing describes approximately 200 MW IT load; this is not a measured operational load. Location is county-level. 2
Locality latitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
Not published
Locality longitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
Not published
State / region Source-disclosed state, province or county when the city is withheld.
Not published
Delivered MW MW Explicitly operating or delivered power, at the evidence date. Power basis defines IT, facility or phase scope. Null if not verified.
Not published
Planned / contracted MW MW Announced expansion or total contracted power; may include delivered phases. Read the power basis and notes; never sum with delivered MW.
200 1
Site scope Editorial classification from the cited operator/site evidence. General cloud presence does not assert site-level GPU inventory; historical projects are not active deployments.
GPU / AI deployment 1

Sources & access dates

  1. Nscale Ward County and Madison GPU financing, 31 August 2026 accessed 2026-11-11
  2. Nscale execution update, 1 October 2026 accessed 2026-11-11
  3. Nscale infrastructure directory, Ward County entry accessed 2026-11-11

Continue the shortlist

North America →Operating deployments →United States →Nscale →All mapped locations →

Discuss capacity at Nscale Ward County

Send your GPU requirements, preferred location, timeline and budget. Name the operators you want to contact.

Email a capacity request

Requests are handled by email at hello@neocloudmap.com.