Nscale / Iceland

Nscale Keflavik / Verne

Nscale runs liquid-cooled NVIDIA GB300 racks at Verne’s Keflavik campus: 7.5 MW live of a 15 MW deployment.

Operational

Sources checked

Verne completed phase 1 in three months with 64 liquid-cooled GB300 racks (April 2026).

Open official site evidenceCompare locationsRequest a quote

Site evidence

Source per value
Operator GPU-cloud provider tied to this physical site.
Nscale 1
City / locality Source-named city, metro or locality. Null when only a county, state or dedicated regional facility is disclosed; no guessed city.
Keflavik 2
Country Country of the physical deployment.
Iceland 1
Evidence status Status supported by the cited evidence. An operational site may also have future expansion; target dates alone do not prove opening.
Operational 4
Facility / partner Named host, owner or development partner; role shown where stated.
Verne 1
Disclosed power MW Read together with Power basis. This may be an IT lease, campus plan, facility capacity or a delivered phase; values must not be summed.
15 1
Power basis Scope, timing and qualification of the disclosed MW. Operational status does not imply all listed MW are live.
7.5 MW deployed in phase 1 of a 15 MW Nscale deployment. 4
GPU platform Site-specific deployed or announced platform. Expansion and future deployment are explicitly marked.
NVIDIA GB300 (Blackwell Ultra) 1
Disclosed GPUs Published count, approximation or lower bound. Read GPU count basis for deployed versus planned scope.
4,600 1
GPU count basis Exact scope of the GPU count, including lower bounds and target years. Counts are not a current availability inventory.
About 4,600 GPUs announced for the full deployment. 1
Interconnect Site-specific networking named in the source; no inference from a provider-wide offer.
Not published
Cooling Cooling design or installed method at the site; expansion scope retained where relevant.
85% liquid cooled; 15% air cooled 1
Evidence date Date of the cited status statement or reporting period. Null means an undated page; accessed dates remain in sources.
2026-04-23 4
Scope notes Research reconciliation, historical qualifications and unresolved delivery questions, with sources.
Verne completed phase 1 in three months with 64 liquid-cooled GB300 racks (April 2026). 4
Locality latitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
64.005 3
Locality longitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
-22.562 3
State / region Source-disclosed state, province or county when the city is withheld.
Not published
Delivered MW MW Explicitly operating or delivered power, at the evidence date. Power basis defines IT, facility or phase scope. Null if not verified.
7.5 4
Planned / contracted MW MW Announced expansion or total contracted power; may include delivered phases. Read the power basis and notes; never sum with delivered MW.
15 1
Site scope Editorial classification from the cited operator/site evidence. General cloud presence does not assert site-level GPU inventory; historical projects are not active deployments.
GPU / AI deployment 1

Sources & access dates

  1. Nscale / Verne 15 MW Iceland infrastructure announcement accessed 2026-11-11
  2. Nscale infrastructure directory, Keflavik entry accessed 2026-11-11
  3. Open-Meteo / GeoNames: Keflavik locality coordinates accessed 2026-11-11
  4. BeBeez: Verne and Nscale complete phase 1, 24 Apr 2026 accessed 2026-11-11

Continue the shortlist

Europe →Operating deployments →Iceland →Nscale →All mapped locations →

Discuss capacity at Nscale Keflavik / Verne

Send your GPU requirements, preferred location, timeline and budget. Name the operators you want to contact.

Email a capacity request

Requests are handled by email at hello@neocloudmap.com.