Location shortlist / 42 sites

Europe

Compare Nordic, British and continental European physical deployments. This view includes 42 sourced records. Delivered and planned MW sit in separate columns, each tied to its source.

Locate sites on the map · Read the capacity definitions

CoreWeave ArasurCoreWeaveArasurSpainGPU / AI deploymentAnnounced—181Reported future lease allocation, not confirmed operating MW.—2026-11-11
CoreWeave at Bulk N01CoreWeaveVenneslaNorwayGPU / AI deploymentAnnounced———NVIDIA GB200 NVL722026-11-11
CoreWeave Barcelona Zona FrancaCoreWeaveBarcelonaSpainGPU / AI deploymentOperational151—15 MW facility capacity at the May 2025 inauguration.NVIDIA H2002026-11-11
CoreWeave Copenhagen DEN01CoreWeaveCopenhagenDenmarkGPU / AI deploymentOperational—22.51Planned IT capacity; majority online, exact delivered MW undisclosed.NVIDIA Blackwell2026-11-11
CoreWeave CrawleyCoreWeaveCrawleyUnited KingdomGPU / AI deploymentOperational———NVIDIA H2002026-11-11
CoreWeave FalunCoreWeaveFalunSwedenGPU / AI deploymentAnnounced———NVIDIA Blackwell (announced cluster)2026-11-11
CoreWeave London DocklandsCoreWeaveLondonUnited KingdomGPU / AI deploymentOperational———NVIDIA H2002026-11-11
CoreWeave Stockholm 4 SouthCoreWeaveStockholmSwedenGPU / AI deploymentOperational————2026-11-11
CoreWeave Stockholm second campusCoreWeaveStockholmSwedenGPU / AI deploymentAnnounced————2026-11-11
Crusoe Keflavik ICE02CrusoeKeflavikIcelandGPU / AI deploymentOperational———NVIDIA DGX GB200 NVL72 / Blackwell (expansion)2026-11-11
Crusoe Tørdal DRA01CrusoeTørdalNorwayGPU / AI deploymentOperational121401Live IT capacity at DRA01.NVIDIA Vera Rubin NVL72 (DRA02 expansion planned for late 2027)2026-11-11
Fluidstack Bosquel former proposalFluidstackBosquelFranceHistorical projectWithdrawn / transferred————2026-11-11
Hyperstack / NexGen NORWAY-1Hyperstack / NexGen—NorwayGPU / AI deploymentOperational————2026-11-11
Nebius Keflavik VerneNebiusKeflavikIcelandGPU / AI deploymentOperational101—Nebius cluster implementation; not Verne campus total.—2026-11-11
Nebius LappeenrantaNebiusLappeenrantaFinlandGPU / AI deploymentUnder construction—3101Up to 310 MW at full deployment; IT/gross not stated—2026-11-11
Nebius LondonNebiusLondonUnited KingdomGPU / AI deploymentAnnounced———NVIDIA Blackwell Ultra (contracted deployment)2026-11-11
Nebius MadridNebiusMadridSpainGPU / AI deploymentOperational———NVIDIA RTX PRO 60002026-11-11
Nebius MäntsäläNebiusMäntsäläFinlandGPU / AI deploymentOperational751—Expanded data center capacity; IT/gross distinction not statedNVIDIA GB300 NVL722026-11-11
Nebius near LilleNebiusLilleFranceGPU / AI deploymentUnder construction—2401240 MW when fully deployed; IT/gross not stated—2026-11-11
Nebius ParisNebiusParisFranceGPU / AI deploymentOperational————2026-11-11
Nscale BlönduósNscaleBlönduósIcelandGPU / AI deploymentStatus unconfirmed————2026-11-11
Nscale Cobalt Park Stargate UKNscaleCobalt ParkUnited KingdomGPU / AI deploymentAnnounced————2026-11-11
Nscale GlomfjordNscaleGlomfjordNorwayGPU / AI deploymentOperational301—Operator-stated operational capacity; expandable to 60 MW; IT/gross split unspecified—2026-11-11
Nscale HayesNscaleHayesUnited KingdomGPU / AI deploymentStatus unconfirmed————2026-11-11
Nscale Keflavik / VerneNscaleKeflavikIcelandGPU / AI deploymentOperational7.541517.5 MW deployed in phase 1 of a 15 MW Nscale deployment.NVIDIA GB300 (Blackwell Ultra)2026-11-11
Nscale LoughtonNscaleLoughtonUnited KingdomGPU / AI deploymentStatus unconfirmed—901Maximum scalable power allocation; not delivered IT load.—2026-11-11
Nscale Narvik / KvandalNscaleNarvikNorwayGPU / AI deploymentUnder construction—2301Planned campus capacity; not verified live IT powerNVIDIA Rubin (planned)2026-11-11
Nscale OsloNscaleOsloNorwayGPU / AI deploymentStatus unconfirmed————2026-11-11
Nscale Sines / Start CampusNscaleSinesPortugalGPU / AI deploymentOperational———NVIDIA Blackwell Ultra2026-11-11
Nscale StavangerNscaleStavangerNorwayGPU / AI deploymentStatus unconfirmed————2026-11-11
Sesterce BosquelSesterceBosquelFranceGPU / AI deploymentAnnounced—1,0001Planned campus or first-phase capacity; no commissioning confirmation.—2026-11-11
Sesterce JämsäSesterceJämsäFinlandGPU / AI deploymentAnnounced—2001Planned campus or first-phase capacity; no commissioning confirmation.—2026-11-11
Sesterce ValenceSesterceValenceFranceGPU / AI deploymentAnnounced—401Planned campus or first-phase capacity; no commissioning confirmation.—2026-11-11
Vultr AmsterdamVultrAmsterdamNetherlandsGeneral cloud footprintOperational————2026-11-11
Vultr FrankfurtVultrFrankfurtGermanyGeneral cloud footprintOperational————2026-11-11
Vultr LondonVultrLondonUnited KingdomGeneral cloud footprintOperational————2026-11-11
Vultr MadridVultrMadridSpainGeneral cloud footprintOperational————2026-11-11
Vultr ManchesterVultrManchesterUnited KingdomGeneral cloud footprintOperational————2026-11-11
Vultr MilanVultrMilanItalyGeneral cloud footprintOperational————2026-11-11
Vultr ParisVultrParisFranceGeneral cloud footprintOperational————2026-11-11
Vultr StockholmVultrStockholmSwedenGeneral cloud footprintOperational————2026-11-11
Vultr WarsawVultrWarsawPolandGeneral cloud footprintOperational————2026-11-11

Other shortlists

  • Operating deployments — Locations with a public operational statement. Expansion capacity may still be planned.
  • Construction & plans — Announced facilities, construction projects and unresolved delivery status.