Crusoe / Norway

Crusoe Tørdal DRA01

Crusoe’s 12 MW DRA01 at Polar’s Tørdal campus in Norway is live; DRA02 adds 40 MW of NVIDIA Vera Rubin NVL72 in late 2027.

Operational

Sources checked

Operating Crusoe Cloud facility; DRA02 expansion belongs to the same campus and is not counted as another site. Additional 40 MW critical IT planned for DRA02 in late 2027; not the total including DRA01.

Open official site evidenceCompare locationsRequest a quote

Site evidence

Source per value
Operator GPU-cloud provider tied to this physical site.
Crusoe 1
City / locality Source-named city, metro or locality. Null when only a county, state or dedicated regional facility is disclosed; no guessed city.
Tørdal 1
Country Country of the physical deployment.
Norway 1
Evidence status Status supported by the cited evidence. An operational site may also have future expansion; target dates alone do not prove opening.
Operational 1
Facility / partner Named host, owner or development partner; role shown where stated.
Polar Data Centers 1
Disclosed power MW Read together with Power basis. This may be an IT lease, campus plan, facility capacity or a delivered phase; values must not be summed.
12 1
Power basis Scope, timing and qualification of the disclosed MW. Operational status does not imply all listed MW are live.
Live IT capacity at DRA01. 1
GPU platform Site-specific deployed or announced platform. Expansion and future deployment are explicitly marked.
NVIDIA Vera Rubin NVL72 (DRA02 expansion planned for late 2027) 1
Disclosed GPUs Published count, approximation or lower bound. Read GPU count basis for deployed versus planned scope.
Not published
GPU count basis Exact scope of the GPU count, including lower bounds and target years. Counts are not a current availability inventory.
Not published
Interconnect Site-specific networking named in the source; no inference from a provider-wide offer.
Not published
Cooling Cooling design or installed method at the site; expansion scope retained where relevant.
Liquid cooling (DRA02 expansion design) 1
Evidence date Date of the cited status statement or reporting period. Null means an undated page; accessed dates remain in sources.
2026-10-21 1
Scope notes Research reconciliation, historical qualifications and unresolved delivery questions, with sources.
Operating Crusoe Cloud facility; DRA02 expansion belongs to the same campus and is not counted as another site. Additional 40 MW critical IT planned for DRA02 in late 2027; not the total including DRA01. 1
Locality latitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
Not published
Locality longitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
Not published
State / region Source-disclosed state, province or county when the city is withheld.
Not published
Delivered MW MW Explicitly operating or delivered power, at the evidence date. Power basis defines IT, facility or phase scope. Null if not verified.
12 1
Planned / contracted MW MW Announced expansion or total contracted power; may include delivered phases. Read the power basis and notes; never sum with delivered MW.
40 1
Site scope Editorial classification from the cited operator/site evidence. General cloud presence does not assert site-level GPU inventory; historical projects are not active deployments.
GPU / AI deployment 1

Sources & access dates

  1. Crusoe Tørdal DRA01 site evidence accessed 2026-11-11

Continue the shortlist

Europe →Operating deployments →Norway →Crusoe →All mapped locations →

Discuss capacity at Crusoe Tørdal DRA01

Send your GPU requirements, preferred location, timeline and budget. Name the operators you want to contact.

Email a capacity request

Requests are handled by email at hello@neocloudmap.com.