Lambda / United States

Lambda Kansas City AI factory

Lambda announced a Kansas City facility conversion for a dedicated customer; subsequent reporting leaves its delivery status unresolved.

Status unconfirmed

Sources checked

Lambda’s October 2025 plan targeted early 2026 and expansion beyond 100 MW. KSHB reported on 3 June 2026 that the Port KC bond application was withdrawn; that alone does not establish project cancellation.

Open official site evidenceCompare locationsRequest a quote

Site evidence

Source per value
Operator GPU-cloud provider tied to this physical site.
Lambda 1
City / locality Source-named city, metro or locality. Null when only a county, state or dedicated regional facility is disclosed; no guessed city.
Kansas City 1
Country Country of the physical deployment.
United States 1
Evidence status Status supported by the cited evidence. An operational site may also have future expansion; target dates alone do not prove opening.
Status unconfirmed 2
Facility / partner Named host, owner or development partner; role shown where stated.
Not published
Disclosed power MW Read together with Power basis. This may be an IT lease, campus plan, facility capacity or a delivered phase; values must not be summed.
24 1
Power basis Scope, timing and qualification of the disclosed MW. Operational status does not imply all listed MW are live.
Announced launch capacity; not verified operating capacity 1
GPU platform Site-specific deployed or announced platform. Expansion and future deployment are explicitly marked.
NVIDIA Blackwell Ultra 1
Disclosed GPUs Published count, approximation or lower bound. Read GPU count basis for deployed versus planned scope.
10,000 1
GPU count basis Exact scope of the GPU count, including lower bounds and target years. Counts are not a current availability inventory.
More than 10,000 planned at launch; lower bound 1
Interconnect Site-specific networking named in the source; no inference from a provider-wide offer.
Not published
Cooling Cooling design or installed method at the site; expansion scope retained where relevant.
Not published
Evidence date Date of the cited status statement or reporting period. Null means an undated page; accessed dates remain in sources.
2026-06-03 2
Scope notes Research reconciliation, historical qualifications and unresolved delivery questions, with sources.
Lambda’s October 2025 plan targeted early 2026 and expansion beyond 100 MW. KSHB reported on 3 June 2026 that the Port KC bond application was withdrawn; that alone does not establish project cancellation. 2
Locality latitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
39.1 3
Locality longitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
-94.579 3
State / region Source-disclosed state, province or county when the city is withheld.
Not published
Delivered MW MW Explicitly operating or delivered power, at the evidence date. Power basis defines IT, facility or phase scope. Null if not verified.
Not published
Planned / contracted MW MW Announced expansion or total contracted power; may include delivered phases. Read the power basis and notes; never sum with delivered MW.
24 1
Site scope Editorial classification from the cited operator/site evidence. General cloud presence does not assert site-level GPU inventory; historical projects are not active deployments.
GPU / AI deployment 1

Sources & access dates

  1. Lambda Kansas City AI factory announcement accessed 2026-11-11
  2. KSHB: Project Blitz withdraws Port KC bond application accessed 2026-11-11
  3. Open-Meteo / GeoNames: Kansas City locality coordinates accessed 2026-11-11

Continue the shortlist

North America →Construction & plans →United States →Lambda →All mapped locations →

Discuss capacity at Lambda Kansas City AI factory

Send your GPU requirements, preferred location, timeline and budget. Name the operators you want to contact.

Email a capacity request

Requests are handled by email at hello@neocloudmap.com.