Lambda / United States
Lambda Kansas City AI factory
Lambda announced a Kansas City facility conversion for a dedicated customer; subsequent reporting leaves its delivery status unresolved.
Lambda’s October 2025 plan targeted early 2026 and expansion beyond 100 MW. KSHB reported on 3 June 2026 that the Port KC bond application was withdrawn; that alone does not establish project cancellation.
Site evidence
Source per value- Operator GPU-cloud provider tied to this physical site.
- Lambda 1
- City / locality Source-named city, metro or locality. Null when only a county, state or dedicated regional facility is disclosed; no guessed city.
- Kansas City 1
- Country Country of the physical deployment.
- United States 1
- Evidence status Status supported by the cited evidence. An operational site may also have future expansion; target dates alone do not prove opening.
- Status unconfirmed 2
- Facility / partner Named host, owner or development partner; role shown where stated.
- Not published
- Disclosed power MW Read together with Power basis. This may be an IT lease, campus plan, facility capacity or a delivered phase; values must not be summed.
- 24 1
- Power basis Scope, timing and qualification of the disclosed MW. Operational status does not imply all listed MW are live.
- Announced launch capacity; not verified operating capacity 1
- GPU platform Site-specific deployed or announced platform. Expansion and future deployment are explicitly marked.
- NVIDIA Blackwell Ultra 1
- Disclosed GPUs Published count, approximation or lower bound. Read GPU count basis for deployed versus planned scope.
- 10,000 1
- GPU count basis Exact scope of the GPU count, including lower bounds and target years. Counts are not a current availability inventory.
- More than 10,000 planned at launch; lower bound 1
- Interconnect Site-specific networking named in the source; no inference from a provider-wide offer.
- Not published
- Cooling Cooling design or installed method at the site; expansion scope retained where relevant.
- Not published
- Evidence date Date of the cited status statement or reporting period. Null means an undated page; accessed dates remain in sources.
- 2026-06-03 2
- Scope notes Research reconciliation, historical qualifications and unresolved delivery questions, with sources.
- Lambda’s October 2025 plan targeted early 2026 and expansion beyond 100 MW. KSHB reported on 3 June 2026 that the Port KC bond application was withdrawn; that alone does not establish project cancellation. 2
- Locality latitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
- 39.1 3
- Locality longitude ° Open-Meteo / GeoNames locality centroid, rounded to four decimals. Not a facility coordinate.
- -94.579 3
- State / region Source-disclosed state, province or county when the city is withheld.
- Not published
- Delivered MW MW Explicitly operating or delivered power, at the evidence date. Power basis defines IT, facility or phase scope. Null if not verified.
- Not published
- Planned / contracted MW MW Announced expansion or total contracted power; may include delivered phases. Read the power basis and notes; never sum with delivered MW.
- 24 1
- Site scope Editorial classification from the cited operator/site evidence. General cloud presence does not assert site-level GPU inventory; historical projects are not active deployments.
- GPU / AI deployment 1
Sources & access dates
- Lambda Kansas City AI factory announcement accessed 2026-11-11
- KSHB: Project Blitz withdraws Port KC bond application accessed 2026-11-11
- Open-Meteo / GeoNames: Kansas City locality coordinates accessed 2026-11-11
Continue the shortlist
North America →Construction & plans →United States →Lambda →All mapped locations →
Discuss capacity at Lambda Kansas City AI factory
Send your GPU requirements, preferred location, timeline and budget. Name the operators you want to contact.
Email a capacity requestRequests are handled by email at hello@neocloudmap.com.